Renovation of existing Servery and Dining Spaces to include;
- New HVAC
- Expansion of existing servery to allow for Marketplace Concept
- Minor renovations to existing kitchen and Dining Services office area to allow for servery expansion
- Upgrade of plumbing and electrical
- Replacement of existing tray drop with more efficient Trayveyor system
- New finishes and furnishings for dining area
Project Data
- Status: Construction completion August 1st, 2008
- Facilities Management Contact: Kathy Gerardi
Financial Data
- Total Cost: $3.5 million
- Project approved and funded through construction.
- Level of Estimate: Construction Document bids.
Project Photos
- Photo 1 · Photo 2 · Photo 3 · Photo 4 · Photo 5 · Photo 6 · Photo 7 · Photo 8 · Photo 9 · Photo 10 · Photo 11 · Photo 12 · Photo 13 · Photo 14 · Photo 15 · Photo 16 · Photo 17 · Photo 18
Marycrest Phase III: Renovation
Renovation of middle section of Floors 1 and 2 to include;
- New HVAC for areas on both floors
- New chapel with sacristy on 2 middle
- 2 new meeting rooms on 2 middle
- New offices for Campus Ministry and Residence Education
- New offices for Residential Properties
- Upgrade of lobby finishes and furniture
- New finishes on 2 middle
- Addition of men and women's restroom near 1st floor lobby
- New front desk in lobby
- Relocation of existing mail boxes
Project Data
- Status: Construction completion August 1st, 2008
- Facilities Management Contact: Kathy Gerardi
Financial Data
- Total Cost: $1.2 million
- Project approved and funded through construction.
- Level of Estimate: Construction Document bids.